Summer

From SOWNWiki

Jump to: navigation, search

Contents

Summer 2007 Work

This page exists for discussing the work which SOWN will be undertaking over the summer. The majority of the work will be carried out by Paul Dart our ECS Employed intern. This pages has been divided into several sections covering the work required. Feel free to expand on the points to list equipment which should be purchased and the approx costs/suppliers. These will be talked over at the weekly meeting before orders are placed.

Infrastructure

SOWN Servers which are needed for any services to exist:

  • Network Diagram (Layer 2 and Layer 3)
    • The latest proposal was this.
  • New Servers with new homes
  • VLAN deployment
    • Already connected: sown-vpn, sown-zepler, sown-nat (and sown-test)
    • Needs (re-)connecting: sown-susu, ford
  • Sown CaptivePortal: We are writing out own which will manage both the campus and sown[at]home nodes all in one foul swoop! 1337

Campus Nodes

Where do we go from here:

  • Equipment List (per node)
  • Node progress
    • Zepler: In process of getting access to roof. Hardware all available. current status - Broken SjH 23:22, 24 May 2008 (BST)
    • SUSU: Up and running
    • Faraday: Node removed - awaiting completion of refurbishment.
    • Chemistry: Intial site survey conducted.


SOWN[at]HOME

see also: Summer/Firmware

A FON-style system for SOWN for users to share their ADSL connections to SOWN users in areas where campus nodes can't reach: